Oomiiqsu (Aboriginal Mother Centre) Update – December 19

WORK COMPLETED:

  • First floor framing 
  • Continue floor joist
  • Backfill side of building
  • Form play area retaining walls

UPCOMING WORK:

  • Finish framing floor
  • Install floor sheathing
  • Layout second floor walls
  • Back framing on first floor.
  • Pour play area retaining walls
  • Finish installing RWL
  • Backfill south side of property
  • Backfill and sidewalk prep on north side of property
  • Excavate for parking retaining walls
  • Layout mechanical and plumbing