Oomiiqsu (Aboriginal Mother Centre) Update – November 20, 2023

WORK COMPLETED:

  • Pour slab for main building
  • Pour added retaining wall
  • Excavated for play area and back retaining walls
  • Excavated for hydro and RWL
  • Started basement under slab plumbing

UPCOMING WORK:  

  • Install basement under slab insulation and VB
  • Install hydro conduit to PMT and electrical room
  • Install storm sump
  • Install below grade RWL
  • Finish perimeter drain
  • Start framing
  • Form back retaining walls