Huu-ay-aht First Nations Celebrates the Bamfield Main Road Reconciliation Project

ANACLA, B.C. – OCTOBER 10, 2023 Today, Huu-ay-aht First Nations hosted a ribbon-cutting ceremony on the Bamfield Main Road at Kilometre 76 to mark the completion of the Bamfield Main Road Reconciliation Project. Following, was a celebration at the House of Huu-ay-aht.

This project started back in 2020 with Huu-ay-aht and the Province sharing the same vision of creating a safer route between Bamfield and Port Alberni, and today both partners have made it a reality.  Providing mitigation towards a safe route is one substantial task completed.

The Bamfield Main Road is an active industrial road. It supports multiple users from industry to residents living in the Bamfield and Ditidaht area and the growing number of visitors. Over the years, the Bamfield Main, known as a dusty gravel road, has put many road users at risk and in some cases taken their lives. Everyone will play a role in continually being a diligent driver for the safety of everyone on the road.

Although the chip seal is complete, our next task is to collaborate on a strategy for maintaining the chip-sealed road and preparing for the economic growth that will come. Working together with partners we will work diligently to ensure the proper steps are taken to secure this investment and vision. 

A project of this size does not happen without strong partnerships and the many workers involved. Huu-ay-aht extends their utmost respect (ʔiisaak) and gratitude to everyone who contributed and the individuals who worked hard and long hours to complete this project.

B.C. supported the project with $25.7 million in 2020, and an additional $10 million in 2023.

Quotes

“Completing the Bamfield Road Reconciliation Project was a top priority for Huu-ay-aht. Working in partnership with the Province of BC, C̓̓awak ʔqin, and Mosaic, together we have made this a reality. We wanted to provide a safer and more reliable route for everyone who travels in Huu-ay-aht territory. With this upgrade, we begin building a strong, self-reliant community and economy for Huu-ay-aht citizens and everyone in the region. We are grateful to everyone who has supported Huu-ay-aht in reaching our vision.”

– Huu-ay-aht First Nations Chief Councillor, John Jack

“The leadership shown by Huu-ay-aht from the outset of this project has been so inspiring. Their perseverance and resolve got them through wildfires, pandemics, rising costs and floods.  The result is that the Bamfield Main Road is now much safer.  This work will have a lasting impact for everyone: community residents, local businesses, and the forestry and tourism industries alike. It will support economic growth and economic recovery for years to come.”

– Minister of Indigenous Relations and Reconciliation, Murray Rankin

“There are many people to hold in our hearts with remembrance and gratitude as we celebrate this moment. The road is the main transportation link between Port Alberni and the communities of Bamfield and Anacla, and it is used for medical, emergency and community access for Huu-ay-aht First Nations members, Bamfield residents, workers, and visitors. These improvements will make the trip to and from Bamfield and Anacla a safer one, bringing peace of mind to everyone who travels that road.”

– MLA for Mid Island-Pacific Rim and Minister of Energy, Mines, and Low Carbon Innovation, Josie Osbourne

-30-

Cutting the cedar ribbon at kilometre 76 on the Bamfield Main Road. Left to right: Huu-ay-aht Councillor Edward R. Johnson, Mosaic, CEO Rob Gough, Huu-ay-aht Chief Councillor John Jack, Former Minister Scott Fraser, Former Huu-ay-aht Chief Councillor Robert Dennis Sr., MP Gord Johns, Western Forest Products, Seanna McConnel, Huu-ay-aht ḥaw̓ił Jeff Cook, Huu-ay-aht Councillor Brad Johnson and Stephen Rayner.

View Official Press Release Here: Click Here

For more information:

Amanda-Lee Cunningham
Communications Manager
Huu-ay-aht First Nations
250-720-7776
amanda.c@huuayaht.org

Bamfield Main Road Update – October 2 -7 , 2023

Bamfield Main Resurfacing Project Header

Crews on the Bamfield Main Road have completed Chip Sealing. During the week of October 2 to 7, 2023, workers will remain on the road, sweeping, cleaning bridge decks, and removing berms.

Please remember that even with the Chip Seal being complete, a pilot vehicle will still be used for some zones where crews will be actively sweeping. Please expect a maximum 15-minute delay.

Important:

Huu-ay-aht has had a number of concerns brought to their attention in regards to vehicles speeding and putting other road users at risk, specifically around narrow sections of the road.

Please be aware of the road signage and obey the speed limit of 60 km/hr. The Bamfield Main is still an active industrial logging road and road users are travelling on the Bamfield Main at their own risk. To ensure safety for everyone, please slow down.

Be aware and watch for construction equipment, flaggers, crews are on the road, and follow pilot vehicles.

The RCMP will be monitoring for safe driving throughout the project and detour.

Please drive with your headlights on and drive with extreme caution.

Bamfield Main Road Update – September 26

Bamfield Main Resurfacing Project Header

September 24 – 30

  • Chip Seal is completed from kilometres 14.3 to 76.
  • Preparation is completed between kilometres 0 to 14
  • A pilot vehicle will used during both sweeping and seal coating operations on the Bamfield Main Road.
  • Delays will be a maximum of 15 minutes.
  • Chip Seal between kilometre 0 to 6 will be taking place this week.
  • Sweeping, cleaning of bridges, and removing berms will be taking place through out the week.

Important:

Huu-ay-aht has had a number of concerns brought to their attention in regards to vehicles speeding and putting other road users at risk, specifically around narrow sections of the road. Please be aware of the road signage and obey the speed limit of 60 km/hr. The Bamfield Main is still an active industrial logging road and road users are travelling on the Bamfield Main at their own risk. To ensure safety for everyone, please slow down.

Be aware and watch for construction equipment, flaggers, crews are on the road, and follow pilot vehicles.  

The RCMP will be monitoring for safe driving throughout the project and detour.

Please drive with your headlights on and drive with extreme caution.

You can also find road updates on our Social Media at: https://www.facebook.com/HuuayahtFN 

Bamfield Main Road Update – September 22, 2023

Bamfield Main Resurfacing Project Header

For the safety of crews working on the Bamfield Main, single-lane alternating traffic with pilot vehicles will be in place where sweeping is occurring. For the safety of all crews working on the road and other road users, please slow down, follow the speed limit,  and drive with extreme caution.

Important:

Huu-ay-aht has had a number of concerns brought to their attention in regards to vehicles speeding and putting other road users at risk, specifically around narrow sections of the road. Please be aware of the road signage and obey the speed limit of 60 km/hr. The Bamfield Main is still an active industrial logging road and road users are travelling on the Bamfield Main at their own risk. To ensure safety for everyone, please slow down.

Be aware and watch for construction equipment, flaggers, crews are on the road, and follow pilot vehicles.  

The RCMP will be monitoring for safe driving throughout the project and detour.

Please drive with your headlights on and drive with extreme caution.

You can also find road updates on our Social Media at: https://www.facebook.com/HuuayahtFN 

Bamfield Main Road Completion Celebration

Bamfield Main Resurfacing Project Header

Huu-ay-aht First Nations would like to invite you to the celebration of completion of the Bamfield Main Road Reconciliation Project on Tuesday, October 10, at the House of Huu-ay-aht at noon. Join us for a meal, and please bring your shawls and drums.


Request for Bid

For this event Huu-ay-aht First Nations is accepting bids for catering in Anacla for Tuesday, October 10, for approximately 200 people. Please submit your menu, bid, and food safe certificate to communications@huuayht.org