WORK COMPLETED:
- Installed waterproof membrane and drainage mat at elevator pit foundation walls.
- Continued forming basement and main building foundation walls.
UPCOMING WORK:
- Complete forming basement foundation walls.
- Backfill around elevator pit foundation walls.
- Continue forming main building footings and walls.