Bamfield Main Road Update – October 11, 2022

Bamfield Main Resurfacing Project Header

For the period of October 11- 16th 2022, the Bamfield Main Road detour will be in place from approximately 36 km to 58 km. Drivers can expect single-lane traffic and delays of up to 15 minutes at two automated flag systems with pilot cars (approximately 68 km and 63.5 km.)

Only industrial traffic will have access through construction areas. All other travellers are required to use the detour.

Speed should not exceed 60 KM per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.

Crews will continue to work on culvert replacement, borrowing, grid placement, and ditching.

Please continue to obey posted speed limits not exceeding 60 KM and slow down around any new construction areas and construction crews and equipment.