Oomiiqsu (Aboriginal Mother Centre) – Update August 28 – September 1, 2023

WORK COMPLETED:

  • Poured basement foundation walls.
  • Stripped basement foundation walls.
  • Continued forming main building footings and foundation walls.

UPCOMING WORK:

  • Pour footings for main building on south side.
  • Form stepped foundation walls.
  • Continue forming main building footings and walls.
  • Install rebar in main building footings and walls.
  • Install main electrical under footing conduit into electrical room.