WORK COMPLETED:
• Finished forming basement foundation walls.
• Continued forming main building footings and foundation walls.
• Paved patches on roadway from off-site civil work.
UPCOMING WORK:
• Pour concrete for basement foundation walls.
• Continue forming main building footings and foundation walls.
• Install mechanical and electrical sleeves and knockouts in main building foundation walls.
• Install rebar in main building footings and foundation walls.